APVG | Technical supervision of reconstruction of structures on Utena Pond on Rašė (Raudesa) River in Utena district
16060
portfolio_page-template-default,single,single-portfolio_page,postid-16060,ajax_fade,page_not_loaded,,hide_top_bar_on_mobile_header,qode-content-sidebar-responsive,qode-child-theme-ver-1.0.0,qode-theme-ver-11.0,qode-theme-bridge,wpb-js-composer js-comp-ver-4.12,vc_responsive

Technical supervision of reconstruction of structures on Utena Pond on Rašė (Raudesa) River in Utena district

Category
Construction
Builder
Utena district municipality administration
Project location
Utena district
Project timeframe
Contract was signed in 25-06-2015 finished in 24-10-2015

While implementing this project, technical supervision services of reconstruction (renovation (first stage)) of structures on Utena Pond on Rašė (Raudesa) River  in Utena district were provided.

 

Technical supervision services, aiming to provide qualified professional and technical assistance to ensure that the ongoing and completed works would comply with the approved projects, with the requirements of the contracting agreement, as well as with the requirements of relevant laws, construction documents and other legislation. During the project, consistent execution of works was supervised, engineering, financial and environmental issues, emerging during the construction period, were addressed, the compliance with the contractual terms, related to the quality and quantity of works, was monitored.

Technical supervisor was responsible for the control of works and materials, supplied by contractor, and their compliance with the requirements of the project. The functions of technical supervision were performed, according to provisions of Law on Construction and Technical Construction Regulation of the Republic of Lithuania STR 1:09:05:2002 “Construction technical supervision”. Reclamation Technical Regulation MTR 2:02:01:2006 “Reclamation structures. The main requirements” was followed.